Project: Roper St. Francis Healthcare Mt. Pleasant Hospital
Location: Mt. Pleasant, South Carolina
Engineer: Freeman White
Construction Manager: BE&K
Mechanical Contractor: TMI (Factory Piped)
Electrical Contractor: TMI (Factory Piped)
Installing Contractor: TMI
Project Description:
(1) 112,000 cfm Custom Penthouse Unit
(1) 125,000 cfm Custom Penthouse Unit
(1) 20,000 cfm Custom Penthouse Unit
Complete turn-key custom penthouse units including:
- AHUs
- Mechanical equipment rooms
- All piping systems
- All power distribution and wiring
- Controls
|
- Installation
- On site testing
- Seismic certification of all equipment and systems
|
Complete supply and installation of equipment including:
- 650 ton Chillers
- Multistack chillers
- Cooling towers
- Roof curbs
- Cooling tower grillage steel
- Boilers
- Steam Generators
- VFDs
|
- Panel boards
- Transfomers
- Pumps
- Hot water heaters
- Expansion tanks
- Storage tanks
- VAV boxes
- Fan coil units
|
Logistics:
Delivery began 17 weeks from approval. Just in time delivery by 25 trucks for installation on site by TMI.