Project: Dublin Methodist Hospital
Location: Dublin, OH

Project Description:
(13) Custom Roof Top Air Handling Units
Logistics:
This project required the units to ship from the factory with Architectual siding installed to eliminate the need for field installed screen walls. In addition, co-ordination efforts to provide “ Just in Time” delivery resulted in (52) sections being shipped and installed over 5 days, eliminating double handling and storage of the unit sections. To further improve on speed of completion and quality all 13 units were shipped pre-piped to a single point connection at the pipe chase.